Air-source heat-pump installation checks

A practical sequence for siting, water-side preparation, condensate, electrical provision, commissioning and handover.

Core idea

A heat-pump installation succeeds as a complete system. The outdoor unit needs free airflow, service access, a stable base and a condensate route that will not create ice or damp problems. The water side needs suitable pipe sizing, cleanliness, insulation, design flow and frost protection. Electrical and control work must match the declared load and the manufacturer’s instructions.

What to recognise

  • Keep discharge and intake air paths clear; recirculated cold air reduces capacity and efficiency.
  • Plan noise, vibration and boundary effects at the chosen operating conditions, not from a catalogue image alone.
  • Flush, fill, vent and balance the water circuit before judging performance.
  • Route and protect condensate so freezing water cannot create a slip hazard or damage the building.
  • Record settings and explain normal defrost, controls and backup-heat behaviour during handover.

Apply it

Work in an order that makes faults traceable: confirm the design duty and emitter circuit, inspect the site, prepare the hydraulic circuit, prove electrical supplies and controls, commission to the manufacturer’s data, then compare measured flow and temperatures with the design. A warm house on handover day does not prove that flow, frost protection or seasonal operation is correct.

Keep the boundary clear

Refrigerant-circuit work, electrical work and structural decisions each have competence requirements. Follow the current manufacturer instructions, planning position and applicable certification route for the actual installation rather than treating an MCS label as a substitute for design evidence.